In
addition to reflecting the new payment legislation, the JCT 2011 edition makes
other changes which include:
- A
revised Insolvency definition in the Termination section.
- The revised Terrorism Cover provisions that were included in JCT's December
2009 Update.
- The provision for appointment of the principal contractor under CDM
Regulations has been
extended to cover that function under the Site Waste Management
Plans Regulations 2008.
- Statutory reference to the Bribery Act 2010.
- Entries in respect of PI insurance relating to asbestos and fungal mould have
been removed.
- Revised retention provisions in the sub-contracts.
The JCT 05 contracts were withdrawn effective 31st December 2012.
Click on the "FREE JCT Documents" for help in selecting the right contract for you, plus other related documents